Transport in MBR City

Everything on this site filed under transport — with the date it was announced and where we read it.

Two cut-paper roads running side by side in a long S-curve across a teal ground, dashed lane lines along each

Transport

A fourth lane on Ras Al Khor and Al Khail

Two roads past MBR City now have four lanes instead of three: Ras Al Khor Road towards Al Khail, and a 1 km stretch of Al Khail towards Abu Dhabi. The RTA counts a third more capacity on each.

Two cut-paper roads meeting at a shallow angle on a warm grey ground, a small ringed disc at the junction

Transport

Al Asayel 80, Al Mustaqbal 70

From 1 November 2026 the RTA raises Al Asayel Street from 60 to 80 km/h between Oud Metha and Al Meydan Street, and Al Mustaqbal Street from 60 to 70 between Sheikh Rashid Road and Al Meydan Street. Both end at MBR City's northern boundary road.

A chain of small cut-paper capsules on a thin track curving across a warm grey ground, one capsule set apart at a stop

Transport

Glydways trial, MBR City listed

The RTA began a four-week trial of Glydways' automated transit pods at Bluewaters on 12 October: four-to-six-seat vehicles on a narrow guideway at up to 50 km/h, moving more than 20,000 passengers an hour. Mohammed Bin Rashid City, MBR City, is one of the corridors the authority says it is studying for a real line.

A pale aqua paper bar on a deep teal ground, filled a quarter of the way along with chalk white, a small sand marker above the fill

Transport

Blue Line reaches 26 per cent

Construction on the Dubai Metro's Blue Line stands at 26 per cent in early September, against a target of 30 per cent by the end of the year and an opening set for 9 September 2029 — three years before the Gold Line reaches Meydan, in MBR City.

A long chalk-white paper tube crossing a deep teal ground, a pale aqua circle at its leading end and a small sand-coloured marker behind it

Transport

First Blue Line tunnel, in two months

Al Wugeisha, a 2,000-tonne boring machine, broke into its first station two months after tunnelling began — more than twice the daily rate achieved on the original Metro. The line opens on 9 September 2029, and MBR City's Gold Line three years after that.

A cut-paper cross-section of ground with a long tunnel bore and small station boxes hanging into it

Transport

The Gold Line is approved: 42 km, entirely underground

Dubai has approved a third metro line — 18 stations from Al Ghubaiba to Jumeirah Golf Estates, AED 34 billion, opening 9 September 2032. It interchanges with Etihad Rail at Meydan, in MBR City.

Construction timeline of the Dubai Metro Blue Line: 10% complete in November 2025, a 30% target for the end of 2026, and opening in September 2029, with a note that the route runs east of MBR City.

Transport

Metro Blue Line reaches 10%

Dubai's 30km, 14-station Blue Line hit 10% completion five months after breaking ground and is targeting 30% by the end of 2026, for a September 2029 opening — on a route that does not serve MBR City.